Revision as of 05:40, 26 November 2025 by Margarkhza (talk | contribs) (Created page with "<html><p> Building Your Dream Home-- Part 3</p><p> </p> Exterior Framing Continues<p> </p>With the homes sub-floor down and the outside walls framed and up, the framing crew was on to the roofing system. Though the roofing system was rather easy in structure with just a 12/12 pitch and no valleys it was a substantial framing endeavor due to just the size and height of it. Your home was 32 feet large by 44 feet in length, and the exterior side walls stood 11 feet high in...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigationJump to search

Building Your Dream Home-- Part 3

Exterior Framing Continues

With the homes sub-floor down and the outside walls framed and up, the framing crew was on to the roofing system. Though the roofing system was rather easy in structure with just a 12/12 pitch and no valleys it was a substantial framing endeavor due to just the size and height of it. Your home was 32 feet large by 44 feet in length, and the exterior side walls stood 11 feet high in the fantastic space. This exterior wall height of 11 feet translated into a roof ridge that was 27 feet off the flooring of the fantastic space. As a result staging was needed to set up the ridge pole and roofing rafters. In addition, since the span from the top of the walls to the ridge was so long, heavy 2x12s were needed for the roof rafters. Within a week, nevertheless, the team had finished the installation of licensed plumber close to me the roof rafters and your house began to handle real shape.

I should comment briefly about the sub-floor and outside walls before I move on.

I decided on using tongue and groove plywood for the sub-flooring rather than OSB/particle board as I was concerned that the OSB was too sensitive to moisture. I was worried about this, both from the construction phase and from regular home usage. I was concerned that during the building and construction phase that snow and ice could possibly lead to harm such as warping. I have seen this before when OSB was utilized on sub-flooring. I was also concerned that throughout the life of the home, that there might be water events, e.g. a leaking dishwashing machine or washer maker that also might also lead to water damage to the flooring. I also believe that plywood is stronger which it would provide for a more strong and rigid floor.

Regarding the exterior wall framing I utilized 2 × 6 construction. This is typical in New England as the additional wall depth permits greater insulation aspects; a should in chillier climates.

Sheathing the Beyond the Home

In order to get plumbing and electrical professionals onto a site normally they desire the home buttoned up. This consists of the roofing system shingled and the doors and windows on. Therefore my framing team moved onto the outside sheathing once the walls and roofing framing were complete.

As with the sub-floor, I once again picked plywood for the exterior sheathing for the exact same reasons pointed out previously. On the exterior walls exterior grade plywood was utilized. On the roofing 5/8 exterior grade plywood was used. I know lots of contractors today utilize OSB for both the walls and roofing system, nevertheless, I still believe for more powerful building plywood is the way to go.

The sheathing effort took about a week to complete. Throughout this time outside windows and doors showed up on the site. Staging the shipment of material lowers theft and insurance coverage risk as well as keeps a less messy construction website. However, as I have indicated earlier, interaction is important when you are doing Just-in-Time product delivery.

Installing Outside Doors and Windows

The setup of the doors and windows was a significant undertaking for this job as the lake profile of the home was actually a wall of windows; 32 feet in width and 27 feet in height. A good deal of engineering had entered into the window design so that the 10 large custom windows would mesh like a jig saw puzzle. This stated, when the windows got here on site and were examined, it was determined that some of them were not built properly to the measurements specified. After much debate with the framing crew, the window supplier and me we reached a compromise on sharing the expense of fixing the windows. The window supplier reclaimed the incorrectly sized windows and the framing crew started the installation of the doors and what windows they could set up. Thankfully the window supplier had the ability to go back to the site with the effectively sized windows within a few days and the building stage did not miss a beat.

Completing the Interior Framing

With the doors and windows installed, the framing team continued to complete the Interior Framing. This was an amazing time, as the rooms began to take real shape. You might now stroll down corridors and into bedrooms and closet locations. Within simply a couple of days the interior walls were complete and the framing crew continued onto the roofing system for the shingling.

I ought to keep in mind that 2 × 4 building and construction was utilized on the interior walls as insulation was not needed on the interior walls.

Shingling the Roof

The last task to finish before the house could be categorized as Buttoned Up was to install the shingles on the roof. Fortunately my framing crew was also able to do this job, therefore getting rid of the need for yet another subcontractor.

I chose a thirty years architectural shingle due to the quality and look I was trying to achieve on the home.

Though relatively a simple roof, it was rather big and the weather was less than congenial. Consequently it took almost 2 weeks to complete this job. Nevertheless, with the roofing complete, my electrical and plumbing contractors were now able to start their work.

Also, with the main home now structurally complete, the framing crew moved onto the garage framing and building stage. As an outcome of staging the garage behind the main home building and construction phase, I had the ability to have subcontractors work in parallel without getting in each others way.

Rough Electric and Plumbing

With the house Buttoned-Up, my Electric and Plumbing technician subcontractors showed up to start the roughing in stage of their particular tasks.

Rough Electric

I had fulfilled a couple of days before on site with the Electric subcontractor to discuss the placement of all the wall outlets and switches, in addition to where the light fixtures would be positioned. During our conversation he marked the wall studs for the positionings of the electric circuitry boxes so that we could imagine the entire electric electrical wiring plan. We likewise marked where the telephone and cable boxes would reside.

During the electrical rough in circuitry phase, the electrician set up all the electrical wiring reliable plumbing repairs boxes and ran wire from packages to where the primary circuit panel box would reside.

Rough Plumbing

As with the Electrical Subcontractor, I had met several weeks previously with the Plumbing Contractor. During this conference we went over the type of heat for the home, along with where the bathrooms and kitchen were to reside in the home. We likewise went over kinds of restroom components consisting of tubs, sinks and toilets. Subsequently, when he appeared on website he brand-new precisely where to run primary drain and supply pipes and vent stacks. He likewise roughed in all of the plumbing for each restroom and cooking area pipes fixture.

Within a week both the Electrical and Rough Pipes specialists had finished their tasks and had successfully passed their particular evaluations.