Revision as of 11:20, 23 August 2025 by Zerianswpx (talk | contribs) (Created page with "<html><p> Building Your Dream Home-- Part 3</p><p> </p> Exterior Framing Continues<p> </p>With the homes sub-floor down and the outside walls framed and up, the framing crew was on to the roofing system. Though the roofing system was rather easy in structure with simply a 12/12 pitch and no valleys it was a considerable framing endeavor due to simply the size and height of it. Your home was 32 feet wide by 44 feet in length, and the exterior side walls stood 11 feet high...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigationJump to search

Building Your Dream Home-- Part 3

Exterior Framing Continues

With the homes sub-floor down and the outside walls framed and up, the framing crew was on to the roofing system. Though the roofing system was rather easy in structure with simply a 12/12 pitch and no valleys it was a considerable framing endeavor due to simply the size and height of it. Your home was 32 feet wide by 44 feet in length, and the exterior side walls stood 11 feet high in the excellent room. This exterior wall height of 11 feet equated into a roof ridge that was 27 feet off the floor of the terrific room. Subsequently staging was needed to set up the ridge pole and roofing rafters. In addition, because the period from the top of the walls to the ridge was so long, heavy 2x12s were required for the roof rafters. Within a week, nevertheless, the team had actually completed the installation of the roofing system rafters and the house started to handle real shape.

I needs to comment briefly about the sub-floor and exterior walls before I move on.

I picked utilizing tongue and groove plywood for the sub-flooring rather than OSB/particle board as I was worried that the OSB was too conscious moisture. I was concerned about this, both from the construction phase and from regular home usage. I was concerned that throughout the construction phase that snow and ice might possibly lead to damage such as warping. I have seen this before when OSB was used on sub-flooring. I was also worried that throughout the life of the home, that there might be water events, e.g. a leaking dishwasher or washer device that likewise could also lead to water damage to the flooring. I likewise believe that plywood is more powerful and that it would attend to a more strong and rigid floor.

Regarding the outside wall framing I utilized 2 × 6 building. This is typical in New England as the additional wall depth allows for greater insulation factors; a must in colder climates.

Sheathing the Beyond the Home

In order to get pipes and electric professionals onto a site normally they desire the home buttoned up. This includes the roofing shingled and the doors and windows on. Therefore my framing team moved onto the outside sheathing once the walls and roof framing were complete.

As with the sub-floor, I once again chose plywood for the outside sheathing for the exact same factors mentioned earlier. On the outside walls exterior grade plywood was Mount Martha plumbing company used. On the roofing 5/8 outside grade plywood was utilized. I know numerous home builders today utilize OSB for both the walls and roofing, however, I still think for more powerful building plywood is the method to go.

The sheathing best plumber Dandenong effort took about a week to complete. During this time outside windows and doors appeared on the site. Staging the delivery of product reduces theft and insurance coverage risk along with keeps a less cluttered construction site. Nevertheless, as I have actually indicated earlier, interaction is important when you are doing Just-in-Time product delivery.

Installing Exterior Doors and Windows

The setup of the doors and windows was a significant endeavor for this task as the lake profile of the home was literally a wall of windows; 32 feet in width and 27 feet in height. A great deal of engineering had actually gone into the window design so that the 10 big custom-made windows would mesh like a jig saw puzzle. This said, when the windows arrived on website and were checked, it was determined that some of them were not built properly to the dimensions defined. After much argument with the framing team, the window supplier and me we reached a compromise on sharing the expense of repairing the windows. The window vendor took back the poorly sized windows and the framing crew began the installation of the doors and what windows they might set up. Thankfully the window vendor was able to return to the site with the correctly sized windows within a few days and the construction stage did not miss out on a beat.

Completing the Interior Framing

With the doors and windows set up, the framing team continued to finish the Interior Framing. This was an interesting time, as the rooms started to take genuine shape. You could now stroll down hallways and into bed rooms and closet areas. Within just a couple of days the interior walls were total and the framing team continued onto the roofing for the shingling.

I need to note that 2 × 4 building was utilized on the interior walls as insulation was not needed on the interior walls.

Shingling the Roof

The last job to complete before the house could be classified as Buttoned Up was to set up the shingles on the roofing. Luckily my framing crew was also able to do this task, therefore eliminating the need for yet another subcontractor.

I chose a 30 year architectural shingle due to the quality and look I was attempting to attain on the home.

Though reasonably a basic roof, it was rather large and the weather was less than hospitable. Subsequently it took almost 2 weeks to complete this job. Nevertheless, with the roofing system total, my electrical and plumbing contractors were now able to begin their work.

Also, with the primary house now structurally complete, the framing crew moved onto the garage framing and building and construction stage. As a result of staging the garage behind the main home building and construction stage, I was able to have subcontractors operate in parallel without getting in each others way.

Rough Electric and Plumbing

With your home Buttoned-Up, my Electric and Plumbing technician subcontractors appeared to begin the roughing in stage of their respective tasks.

Rough Electric

I had met a couple of days before on website with the Electric subcontractor to talk about the positioning of all the wall outlets and switches, in addition to where the lights would be positioned. During our discussion he marked the wall studs for the placements of the electrical electrical wiring boxes so that we could imagine the whole electric circuitry plan. We also marked where the telephone and cable boxes would reside.

During the electrical rough in circuitry stage, the electrical contractor set up all the wiring boxes and ran wire from the boxes to where the primary circuit panel box would reside.

Rough Plumbing

As with the Electrical Subcontractor, I had fulfilled emergency plumber Baxter several weeks previously with the Plumbing Professional. Throughout this meeting we talked about the type of heat for the home, in addition to where the bathrooms and cooking area were to live in the home. We also went over kinds of bathroom components consisting of tubs, sinks and toilets. Subsequently, when he showed up on website he new precisely where to run main drain and supply pipelines and vent stacks. He also roughed in all of the pipes for each bathroom and kitchen area plumbing fixture.

Within a week both the Electrical and Rough Plumbing professionals had completed their tasks and had successfully passed their respective inspections.