Revision as of 20:07, 11 August 2025 by Lynethzevc (talk | contribs) (Created page with "<html><p> Structure Your Dream Home-- Part 3</p><p> </p> Exterior Framing Continues<p> </p>With the homes sub-floor down and the exterior walls framed and up, the framing team was on to the roof. Though the roofing system was rather simple in structure with just a 12/12 pitch and no valleys it was a significant framing endeavor due to just the size and height of it. Your home was 32 feet large by 44 feet in length, and the outside side walls stood 11 feet tall in the exc...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigationJump to search

Structure Your Dream Home-- Part 3

Exterior Framing Continues

With the homes sub-floor down and the exterior walls framed and up, the framing team was on to the roof. Though the roofing system was rather simple in structure with just a 12/12 pitch and no valleys it was a significant framing endeavor due to just the size and height of it. Your home was 32 feet large by 44 feet in length, and the outside side walls stood 11 feet tall in the excellent room. This outside wall height of 11 feet translated into a roofing system ridge that was 27 feet off the floor of the excellent room. Consequently staging was needed to set up the ridge pole and roofing system rafters. In addition, because the period from the top of the walls to the ridge was so long, heavy 2x12s were needed for the roof rafters. Within a week, nevertheless, the group had actually finished the installation of the roof rafters and the house began to take on genuine Somerville plumbing repairs shape.

I needs to comment briefly about the sub-floor and exterior walls before I move on.

I chose utilizing tongue and groove plywood for the sub-flooring rather than OSB/particle board as I was concerned that the OSB was too sensitive to moisture. I was concerned about this, both from the building and construction stage and from regular home use. I was concerned that throughout the building and construction stage that snow and ice could possibly cause harm such as warping. I have seen this before when OSB was used on sub-flooring. I was also worried that throughout the life of the home, that there could be water events, e.g. a dripping dishwasher or washer device that likewise might likewise lead to water damage to the floor. I likewise believe that plywood is more powerful which it would provide for a more strong and rigid floor.

Regarding the exterior wall framing I used 2 × 6 construction. This is typical in New England as the additional wall depth permits higher insulation elements; a should in cooler climates.

Sheathing the Beyond the Home

In order to get plumbing and electric professionals onto a site usually they want the home buttoned up. This includes the roofing shingled and the doors and windows on. Hence my framing team moved onto the exterior sheathing once the walls and roofing framing were complete.

As with the sub-floor, I again picked plywood for the outside sheathing for the same reasons pointed out previously. On the outside walls exterior grade plywood was used. On the roofing 5/8 exterior grade plywood was utilized. I know lots of contractors today use OSB for both the walls and roofing system, however, I still believe for more powerful building plywood is the way to go.

The sheathing effort took about a week to complete. During this time exterior windows and doors appeared on the website. Staging the shipment of material lowers theft and insurance risk along with keeps a less messy building and construction site. However, as I have indicated previously, interaction is crucial when you are doing Just-in-Time product delivery.

Installing Outside Doors and Windows

The installation of the doors and windows was a major endeavor for this project as the lake side view of the home was literally a wall of windows; 32 feet in width and 27 feet in height. A great deal of engineering had actually gone into the window design so that the 10 big custom-made windows would fit together like a jig saw puzzle. This stated, when the windows got here on site and were examined, it was figured out that a few of them were not built correctly to the dimensions specified. After much debate with the framing team, the window supplier and me we reached a compromise on sharing the expense of fixing the windows. The window vendor took back the improperly sized windows and the framing team began the setup of the doors and what windows they could install. Thankfully the window vendor had the ability to go back to the website with the effectively sized windows within a few days and the construction phase did not miss a beat.

Completing the Interior Framing

With the doors and windows set up, the framing team proceeded to finish the Interior Framing. This was an amazing time, as the spaces started to take genuine shape. You could now stroll down corridors and into bedrooms and closet areas. Within simply a few days the interior walls were total and the framing crew continued onto the roofing system for the shingling.

I need to note that 2 × 4 building was used on the interior walls as insulation was not needed on the interior walls.

Shingling the Roof

The last task to finish before the house could be categorized as Buttoned Up was to set up the shingles on the roofing. Fortunately my framing crew was also able to do this task, thus getting rid of the need for yet another subcontractor.

I picked a 30 year architectural shingle due to the quality and look I was attempting to accomplish on the home.

Though relatively a simple roofing, it was rather large and the weather was less than congenial. Consequently it took nearly 2 weeks to finish this job. Nevertheless, with the roofing complete, my electrical and pipes professionals were now able to start their work.

Also, with the primary home now structurally complete, the framing crew moved onto the garage framing and building and construction phase. As a result of staging the garage behind the main home building and construction phase, I had the ability to have subcontractors work in parallel without getting in each others way.

Rough Electric and Plumbing

With your house Buttoned-Up, my Electric and Plumber subcontractors appeared to begin the roughing in stage of their respective tasks.

Rough Electric

I had fulfilled a few days before on site with the Electric subcontractor to talk about the positioning of all the wall outlets and switches, along with where the lighting fixtures would be situated. During our conversation he marked the wall studs for the placements of the electrical circuitry boxes so that we might envision the entire electrical electrical wiring plan. We likewise marked where the telephone and cable boxes would reside.

During the electrical rough in wiring stage, the electrician set up all the wiring boxes and ran wire from the boxes to where the main circuit panel box would reside.

Rough Plumbing

As with the Electrical Subcontractor, I had actually satisfied several weeks earlier with the Plumbing Contractor. During this conference we went over the form of heat for the home, along with where the bathrooms and cooking area were to reside in the home. We likewise went over kinds of restroom components including tubs, sinks and toilets. Subsequently, when he showed up on website he new precisely where to run primary drain and supply pipelines and vent stacks. He also roughed in all of the pipes for each restroom and kitchen pipes fixture.

Within a week both the Electrical and Rough Plumbing professionals had finished their tasks and had effectively passed their respective evaluations.